National permitting dataset exposes housing chokepoint

Updated: 2026.09.25 1H ago 1 sources
A standardized, nationwide permitting database (60 cities in the new paper) lets researchers measure permit‑approval durations and directly link them to building pace and rents. The new evidence shows permitting time explains a large share (30–43%) of cross‑city differences in project completion, and that permitting has generally slowed since 2000. — If permitting durations are a measurable, substantial driver of slow housing supply, targeted permit‑process reforms become a specific, politically actionable lever to expand supply and reduce housing costs.

Sources

How to kill housing with paperwork
Milan Singh 2026.09.25 100% relevant
The D'Amico, Soltas, and Wang paper and its centralized permitting data for 60 U.S. cities, plus the headline finding that permitting accounts for 30–43% of the slowest‑vs‑fastest city completion gap and that cities like Boston and San Francisco have permitting lags longer than build times in Indianapolis.